AnsweredAssumed Answered

Scheduled Reporting Question

Question asked by latpoly on Mar 20, 2012
Latest reply on Mar 21, 2012 by Corey Bodzin

We're really happy to see the scheduled reporting ability in the new version released recently.  That said, I have a question...

 

1.) Scenario:

     - Weekly scan of servers that launches at 06:00 and always has completed by 10:00. 

     - Have an automatic report scheduled to launch at 13:00 the same day. 

          Idea is to have a scheduled report using the data obtained at the 06:00 scan.

      ISSUE:  The report generated did NOT show the latest scan results.  It was a week old.

 

I ran this same report today manually (via Reports->Templates and using "Run") and the report shows the current data (as would be expected).

 

What are we missing here?

Outcomes